If the trip of overload branch should cause cascading overload inside the corresponding transmission section
rapid overload control should be executed within the time delay of overload protection. The protected object is the whole transmission section
and it is ensured that no branch in the section will be overloaded while power flow of the whole section is decreased. The calculation of integrative sensitivity either neglects normal branches
or is just the algebraic sum of sensitivity of the overload branch and branches near the limit
which cannot reflect the node's capability to alleviate overload on the whole section more reasonably. In addition
prioritization of control nodes
selection of node pairs and constraint conditions of the adjustment amount are still imperfect. Thus
in inheriting the general idea of integrative sensitivity algorithm and making up for the defects
this paper holds that integrative sensitivity is the weighted sum of sensitivity of overload branches and normal branches. Then the classification and operation sequence of control nodes should be determined. And the sensitivity of node to branch and integrative sensitivity are all used to prioritize control nodes. In addition
the principle of ensuring safety of the whole section is added to the selection of node pairs and the power limit of the slack generator is considered. Reverse constraints are added to keep power flow from increasing reversely with too much adjustment. The rapidity and validity of the proposed algorithm is verified by calculation results of a certain actual system.