Access to distributed generators(DGs)and changes in network structure have increased the complexity of state estimation and measurement placement in the active distribution network(ADN). A multi-objective mathematical model of measurement placement in the ADN is established that takes into account both the cost of placement and estimation accuracy of different network structures
in which the output uncertainty of DG is also considered. The output uncertainty of DG is modeled as a Gaussian mixed model(GMM)
and the correlation of DG is described by the off-diagonal elements in a measurement covariance matrix. In addition
the analytic hierarchy process(AHP)is used to determine the impact factors of the cost of placement
the mesh network as well as other network structures. The measurement placement is determined by the greedy algorithm. Simulation results based on IEEE 33-bus and a 119-bus distribution network have verified the efficiency and feasibility of the method proposed. This work is supported by National Natural Science Foundation of China(No. 51177093).
Distribution Network Restoration Decision Considering Risk of State Estimation Error in Restoration Process
Time-varying Virtual Inertia and State Estimation of Grid-following Converter Based on Maximum Correntropy Criterion and Polynomial Chaos Kalman Filter
Forecasting-aided State Estimation for Distribution Networks Based on Event-triggering Encryption
Related Author
ZHU Kaiyu
LIN Jikeng
HAO Lili
KAN Yizhou
XUE Yusheng
XUE Feng
WANG Yuhong
WANG Xueke
Related Institution
College of Electronics and Information Engineering, Tongji University
College of Electrical Engineering & Control Science, Nanjing Tech University
State Grid Electric Power Research Institute (NARI Group Corporation)
School of Electrical Engineering, Sichuan University