it is essential for smooth network reconstruction to identify a safe and effective units’ restoration sequence. Based on the definition of unit’s restoring risk and taking the duration into consideration
the concept of risk of electrical energy loss during the network reconfiguration is further proposed. Through integration of crossover particle swarm optimization and Floyd algorithm
the risk of electrical energy loss can be minimized by means of detailed simulation of network reconfiguration. As a result
the optimal units’ restoration sequence with higher operational reliability as well as the best technical performance is resolved. In particular
investigation on the effect of the unit’s off-line duration on unit’s starting and reconfiguration progress is made closer to field situation by calling the embedded simulation program of thermal unit’s starting and load picking-up. The outcome of its application on the New England 10-unit 39-bus power system indicates the validity of the method proposed. This work is supported by National Natural Science Foundation of China (No. 51077052).
Optimization of Post-typhoon Rush Repair Strategy for Distribution Network Considering Information Integration of Traffic Network and Distribution Network
Optimization Method for Partition and Interconnection of Multi-infeed DC Receiving-end Power System
土耳其“3·31”大停电事故分析及启示
网架重构过程中线路潮流越限消除的网络调整策略
Related Author
GU Xueping
GAO Qian
LIU Yan
Kang CHANG
Shaofeng LIU
Yunyun XIE
Shangxuan LI
Chen YU
Related Institution
North China Electric Power University
School of Automation, Nanjing University of Science and Technology
Tongxiang Power Supply Company of State Grid Zhejiang Electric Power Co., Ltd., Tongxiang
State Key Laboratory of Smart Grid Protection and Control
NARI Group Corporation(State Grid Electric Power Research Institute)