Verification of secondary circuits in process levels plays a significant role in the commissioning of smart substation secondary systems. According to comparison of secondary circuit files
this paper proposes an approach to generation of commissioning schemes for the process level and safety measures by analyzing the relationship between the secondary circuit file and commissioning items. In terms of data links
communication parameters
and data channels
an analysis is made on the differences of secondary circuits in configuration files of different versions
and then the corresponding commissioning items are determined based on the differential secondary circuits. The secondary circuits associated with devices in the subsystem commissioning are analyzed to divide the security interfaces between testing devices and operational devices. The approach presented is expected to provide effective guides for the secondary system commissioning of smart substation extension and reconstruction projects as well as adoption of safety measures. This work is supported by Jiangsu Provincial Natural Science Foundation of China (No. BK20140114) and State Grid Corporation of China.