储能电站并网测试技术研究与实现
摘要
随着储能技术及大型储能电站建设的不断发展
亟待对储能电站进行并网测试以保证其并网后安全运行。首先根据储能电站构成
分析了并网测试指标及具体测试方法;其次
在保证被测储能系统完整性的前提下
研制开发了储能电站并网一体化测试平台
并详细介绍了该平台的软硬件开发及功能设计方案;最后
基于测试平台工程应用场景
介绍了测试装置现场接线方式
提出了储能电站并网测试实施方案。实际工程应用表明了所提出的测试平台及测试方案的可行性。
Abstract
With the continuous development of energy storage technology and the construction of large-scale energy storage power station
the test of energy storage station is necessary for further study to ensure the safety and normal operation after interconnecting to power grid. Firstly
test indicators and specific testing methods are analyzed based on the configuration of energy storage station. Then
an integrated test bench is developed based on the integrity of energy storage station and the interconnecting network. The hardware architecture and program structure of the proposed test bench and the function design are described in detail. Finally
according to the project scenario of test bench
the wiring diagram of test devices is described and the implementation of the test program is proposed. The practical application shows the feasibility of the proposed test bench and its supporting program. This work is supported by State Grid Corporation of China.
Bi-level Optimization Strategy of Grid-side Multiple Energy Storage Stations Considering Available Capacity and Frequency Regulation Cost
Related Author
LI Junhui
SONG Qinglong
GUO Qi
YAN Jun
LI Cuiping
HAO Qianpeng
Related Institution
Key Laboratory of Modern Power System Simulation and Control & Renewable Energy Technology, Ministry of Education (Northeast Electric Power University)