Relay setting computation is a fundamental task for power grid safety. To meet the construction requirements of the large-scale operation system
Jiangxi Power Dispatch Center has realized province-prefecture-county integrated relay protection setting calculation on the operation management system (OMS). Integrated setting calculation database is established
and ‘one grid
one set of data
multiple systems sharing’ is realized. Data merging between province
prefecture and county dispatch centers is completed
and ‘county operator compute
prefectural operator check’ is achieved. Setting calculation management process is improved
and closed-loop management in dispatch center as well as between dispatch center and operating department is realized. The contents presented have been successfully applied in an all-round way in Jiangxi power grid
and the whole process management level of province-prefecture-county setting calculation is enhanced.