Through the simulation analysis of large-scale power system, it is found that the out-of-step generators may behave in two groups, the main out-of-step generator groups and the minor out-of-step generator groups. The main out-of-step generator groups can determine the out-of-step center interface tie-lines of large-scale power system, but the minor out-of-step generator groups cannot. This phenomenon facilitates a method of capturing the out-of-step center interface tie-lines, based on searching the lowest voltage points(center of out-of-step) during the system out-of-step state. By doing so, the main out-of-step generator groups can be identified. But the method maybe fails to split the minor out-of-step generators into the correct coherent out-of-step generator groups. Hence, in engineering practice, the generators which are likely to be in the minor ou-of-step groups should be equipped with the out-of-step separation equipment based on the off-line system analysis. Thus with the backup of the separation devices, further accident will be avoided.